Shivpujan Rampratap Gaur v. The Tahsildar, Borivali, Mumbai 4 ORS.
nilegaonkar 54-wp-861.2018.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION NO. 861 OF 2018 Shivpujan Rampratap Gaur ... Petitioner
Versus
The Tahsildar, Borivali, Mumbai and Ors.
...
Respondents Mr. Sujay Gawade a/w Anita Dubey for the Petitioner. Mr. Himanshu Takke, AGP for the respondent nos.. 1 to 5 State. CORAM : B.P. DHARMADHIKAKRI & REVATI MOHITE DERE, JJ.
DATE :
FEBRUARY 21, 2019 P.C.:
1.
It is not in dispute that controversy is covered by order dated 21st December, 2018, passed by this Court.
2.
A perusal of Appellate Order passed by the Respondent No.4 shows that it expressly mentions that notice impugned in Appeal is not passed under the Maharashtra Slum Areas (Improvement, Clearance and Redevelopment) Act, 1971 ( for short 'the said Act'). 3.
The notice dated 30th May, 2017, issued by the Respondent No.1 clearly mentions the provisions of Section 3(z)(2)(4) of the said
nilegaonkar 54-wp-861.2018.odt Act. Thus, observations in impugned order of Respondent No.4 is itself perverse.
4.
We, therefore, quash and set aside that order dated 29th September, 2017 and restore the Appeal back to the file of Respondent No.4.
5.
Petitioner to appear before the Respondent No.4 on 14th March, 2019. On that day, Respondent No.4 shall hear the Petitioner and take fresh decision, as per law, within eight weeks. 6.
Writ Petition is accordingly disposed of.
(REVATI MOHITE DERE, J.) (B.P. DHARMADHIKARI, J.)