← Library
Bombay High CourtIA/1874/2019

Bhaskar Ramaih Nadar v. The Official Liquidator (Mansukh Industries Ltd (In Liqn)

2019-01-011 pages

kvm 1/1 25-IA 1 in CP228.99

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 1 OF 2019 In COMPANY PETITION NO. 228 OF 1999 Bhaskar Ramih Nadar ..... Applicant

IN THE MATTER BETWEEN

Rajendra Chemexport Pvt. Ltd.

..... Petitioner

VERSUS

The Official Liquidator of M/s.Mansukh Industries Ltd. (In Liqn.) .... Respondent Ms.Namrata Shenoy for the Applicant.

Mr.Mahendhar Aithe, Company Prosecutor for the Official Liquidator present.

CORAM :

R.D. DHANUKA, J.

DATE :

19th DECEMBER, 2019 P.C.

Heard learned counsel for the applicant and the learned Company Prosecutor. Delay of 1 year and 8 months in filing affidavit of claim is explained in paragraphs 6 to 8 of the interim application. The reasons recorded therein are accepted. Interim application is made absolute in terms of prayer clauses (a) and (b). No order as to costs. [R.D.DHANUKA, J.]