Noorullah Shaikh v. The Official Liquidator Of Gol Offshore Limited
kvm 1/1 8-IA 20 in CP756.14
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 20 OF 2019 IN COMPANY PETITION NO. 756 OF 2014 Noorullah Shaikh ..... Applicant
IN THE MATTER BETWEEN
Export Import Bank of India ..... Petitioner
VERSUS
The Official Liquidator of M/s.GOL Offshore Ltd. (in Liqn.) ..... Respondent Ms. Molina Thakur for the Applicant.
Mr.Mahendhar Aithe, Company Prosecutor for the Official Liquidator present.
CORAM :
R.D. DHANUKA, J.
DATE :
19th DECEMBER, 2019 P.C.
Heard learned counsel for the applicant and the learned Company Prosecutor. There is delay of 133 days in filing the affidavit of claim of the applicant. Delay is explained sufficiently in paragraphs 4 to 7 of the interim application and are accepted. Interim application is made absolute in terms of prayer clause (a). No order as to costs. [R.D.DHANUKA, J.]