Bombay High CourtCP/508/2016withdrawn
Ultratech Cement Ltd v. Neelam Finance Bombay Private Limited Cin U65921mh1996ptc099161
2017-04-05Hon'Ble Shri Justice R.D. Dhanuka1 pages
903-cp508-16 vai
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY PETITION NO.508 OF 2016 Ultra Tech Cement
...Petitioner
V/s.
Neelam Finance Bombay Pvt. Ltd.
...Respondent
Ms.Tejaswi Ghag i/b Mr.Sahil Mahajan for the Petitioner. Mr.Sandeep Bhagwat for the Respondent.
CORAM : R.D. DHANUKA, J.
DATE : 5TH APRIL, 2017.
P.C. :- 1.
Learned counsel appearing for the petitioner seeks liberty to withdraw this petition on the ground that the matter is settled out of Court.
2.
The company petition is dismissed as withdrawn in view of the settlement arrived at between the parties out of Court. No order as to costs.
(R.D. DHANUKA, J.) 1/1