The Executive Engineer, Minor Irrigation Dept. Zp, Ahmednagar v. The State Of Mah And ORS
973(iii) delay.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO.2798 OF 2013 IN FAST/155/2013 WITH CA/2802/2013 IN FAST/137/2013 THE EXECUTIVE ENGINEER, MINOR IRRIGATION DEPT. ZP, AHMEDNAGAR
VERSUS
THE STATE OF MAHARASHTRA AND ORS .....
Mr. S.T. Shelke, Advocate for Applicants.
Mr. R.B. Bagul, AGP for Respondent No.1/State. .....
CORAM : SMT. VIBHA KANKANWADI, J.
DATE : 06th SEPTEMBER, 2019.
ORDER :
.
Both these applications have been filed for getting the delay of 335 days condoned in filing first appeals. The acquiring body intends to challenge the judgment and award passed by the learned reference Court. However, there is delay. Respondents/original claimants are served in Civil Application No.2802/2013, those claimants are represented by Advocate, however, the learned Advocate is absent. Under such circumstance, whatever reasons have been given in the applications have gone unchallenged on record. Hence, delay stands condoned.
973(iii) delay.doc 2.
Civil Application stands allowed and disposed of accordingly. 3.
Registry to verify and register the first appeals and place them for further consideration on 14.10.2019.
(SMT. VIBHA KANKANWADI, J.) SCM