Dilip Madhavrao Bobade And Others v. The State Of Maharashtra Through Its Secretary And Others
2025:BHC-AUG:1160-DB 612.25wp etc (1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 969 WRIT PETITION NO. 612 OF 2025 Dilip Madhavrao Bobade Bappasaheb Ashruba Bobade Laxman Ganpatrao Bobade Sarjerao Vitthal Kapse Rambhau Santaram Madane Shrimant Rambhau Madane
VERSUS
1. The State of Maharashtra, thr. its Secretary, Department of Public Works, Mumbai
2. The District Collector, Beed,
3. The Deputy Collector (Land Acquisition), Jayakwadi Project, Beed
4. The Executive Engineer, PWD, Beed ....
Mr M. D. Narwadkar, Advocate h/f Mr A. B. Hawale, Advocate for petitioners Mr S. V. Hange, A.G.P. for respondents/State CORAM : MANGESH S. PATIL AND PRAFULLA S. KHUBALKAR, JJ.
DATE : 14th January, 2025 PER COURT:
1.
The petitioners' application under Section 80 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 has been closed for passing final order as is mentioned in the Roznama dated 12/08/2024. A similar order has already been passed in someone else's matter from the same award.
612.25wp etc (2) 2.
The learned A.G.P., on instructions, submits that the petitioners' application would be decided as expeditiously as possible. 3.
The writ petition is disposed of directing respondent No.3 to pass a final order, as expeditiously as possible and in any case within a period of four weeks, if it has not already been passed. (PRAFULLA S. KHUBALKAR, J.) (MANGESH S. PATIL, J.) sjk