← Library
Bombay High CourtCA/806/2018disposed offdismissed for default

The Reliance General Insurance Co. Ltd., Thr Its Manager, Aurangabad v. Afsar Sha S/O Babu Sha And ORS

2018-08-10Hon'Ble Shri Justice V.L. Achliya1 pages

979-CA-806-2018

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 979 CIVIL APPLICATION NO. 806 OF 2018 IN FAST/600/2018 THE RELIANCE GENERAL INSURANCE CO. LTD., THR ITS MANAGER, AURANGABAD

VERSUS

AFSAR SHA S/O BABU SHA AND ORS ...

Advocate for Applicant : Mr. S.S. Dargad h/f Mr. Chapalgaonkar S.G. Advocate for Respondent No.2 : Mr. Jiwan J. Patil ....

CORAM : V.L. ACHLIYA, J.

DATED : 10th AUGUST, 2018 PER COURT:- 1.

The applicant - appellant has moved this application for condonation of 9 days delay in filing the appeal against the impugned judgment and award passed by the Tribunal. 2.

Heard learned counsel for the applicant and the respondent no.2. Respondent No.1 though served, absent.

3.

Considering the cause assigned for condoning the delay, I am of the view that sufÏcient cause has been made out to condone the delay.

4.

Accordingly, the application is allowed in terms of prayer clause "B". Appeal be registered.

5.

Civil application be marked as disposed of.

( V.L. ACHLIYA ) JUDGE SPR