The Reliance General Insurance Co. Ltd., Thr Its Manager, Aurangabad v. Afsar Sha S/O Babu Sha And ORS
979-CA-806-2018
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 979 CIVIL APPLICATION NO. 806 OF 2018 IN FAST/600/2018 THE RELIANCE GENERAL INSURANCE CO. LTD., THR ITS MANAGER, AURANGABAD
VERSUS
AFSAR SHA S/O BABU SHA AND ORS ...
Advocate for Applicant : Mr. S.S. Dargad h/f Mr. Chapalgaonkar S.G. Advocate for Respondent No.2 : Mr. Jiwan J. Patil ....
CORAM : V.L. ACHLIYA, J.
DATED : 10th AUGUST, 2018 PER COURT:- 1.
The applicant - appellant has moved this application for condonation of 9 days delay in filing the appeal against the impugned judgment and award passed by the Tribunal. 2.
Heard learned counsel for the applicant and the respondent no.2. Respondent No.1 though served, absent.
3.
Considering the cause assigned for condoning the delay, I am of the view that sufÏcient cause has been made out to condone the delay.
4.
Accordingly, the application is allowed in terms of prayer clause "B". Appeal be registered.
5.
Civil application be marked as disposed of.
( V.L. ACHLIYA ) JUDGE SPR