Ajay Sunil Nainwad v. The State Of Maharashtra Through Its Secretary And Another
(1) 18 WP 439.2025.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 18 WRIT PETITION NO. 439 OF 2025 AJAY SUNIL NAINWAD
VERSUS
THE STATE OF MAHARASHTRA THROUGH ITS SECRETARY AND ANOTHER ...
Mr. Chandrakant Thorat, Advocate for the petitioner. Mr. M.M. Nerlikar, A.G.P. for respondents / State. ...
CORAM :
MANGESH S. PATIL & PRAFULLA S. KHUBALKAR, JJ.
DATED :
13 JANUARY 2025 ORDER:- .
Petitioner's proposal has been awaiting adjudication by respondent No.2 Scheduled Tribe Certificate Verification Committee since 2018. He wants it now for undertaking further education.
2.
Learned A.G.P., on instructions, submits that the Committee would need five months for deciding the proposal. 3.
We dispose of the petition directing respondent No.2 to finally decide the petitioner's proposal as expeditiously as possible and in any case within sixteen weeks. (PRAFULLA S. KHUBALKAR) (MANGESH S. PATIL) JUDGE JUDGE VD_Dhirde