IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 902 WRIT PETITION NO.700 OF 2020 THERMAL POWER STATION CONTRACTORS AND SUPPLIERS ASSOCIATION THROUGH ITS AUTHORIZED SIGNATORY

VERSUS

THE STATE OF MAHARASHTRA AND OTHERS ...

Advocate for Petitioner : Mr. Ajinkya Kale h/f Mr. S. B. Talekar & Mr. A. S. Kulkarni.

AGP for Respondent/s-State : Mr. S. G. Sangle. Advocate for Respondent Nos.3 & 4 : Mr. Gaikwad Anil M. Advocate for Respondent No.5 : Mr. Choudhari A. G. Advocate for Respondent No.6 : Mr. Shashikant Chalikwar h/f Mr. Nagargoje Mahadeo V., Mr. S. R. Sapkal & Mr. P. R. Katneshwarkar.

...

CORAM : RAVINDRA V. GHUGE, AND S. G. MEHARE, JJ.

DATE : 21.08.2021 PER COURT :- 1.

The learned advocate has placed on record a communication dated 09.08.2021 received by him from the petitioners, along with the circulation note that was moved on 17.08.2021.

2.

It is submitted that the petitioners have instructed the learned advocate to withdraw this petition, as they do not wish to prosecute the same.

902-WP.700-20.odt 3.

In view of the above, this petition is disposed off, as withdrawn.

(S. G. MEHARE, J.) (RAVINDRA V. GHUGE, J.) ...

vmk/-