The Ex. Engineer, Irrigation Project Div. Osmanabad Thr G.M.I.D.C., Aurangabad v. Virnath Kashinat Tongale (Died) Mahadevi And ORS
26-ca.9538.21.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO.9538 OF 2021 IN FAST/901/2021 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT DIVISION, OSMANABAD, THROUGH G.M.I.D.C., AURANGABAD
VERSUS
VIRNATH KASHINAT TONGALE (DIED) MAHADEVI AND ORS WITH CA/9540/2021 IN FAST/1277/2021 WITH CA/9544/2021 IN FAST/1261/2021 WITH CA/9545/2021 IN FAST/1261/2021 WITH CA/9547/2021 IN FAST/1272/2021 WITH CA/9546/2021 IN FAST/1272/2021 WITH CA/9542/2021 IN FAST/1267/2021 WITH CA/9539/2021 IN FAST/901/2021 WITH CA/9541/2021 IN FAST/1277/2021 WITH CA/9543/2021 IN FAST/1267/2021 ---- Mr.M.C.Swami, Advocate for applicants Mr.Y.G.Gujrati, AGP for respondent nos.5 and 6 ---- CORAM : R.G. AVACHAT, J.
DATE : DECEMBER 17, 2021 ORDER :- It is informed that the respondents-claimants have also filed appeal for enhancement of compensation. The applications for condonation of delay are allowed in terms of prayer clause (B). In appeals:- 2.
Issue notice to the respondents, returnable after eight weeks. Learned AGP waives notice for respondent nos.5 and 6.
26-ca.9538.21 In stay applications:- 3.
Issue notice to the respondents, returnable after eight weeks. Learned AGP waives notice for respondent nos.5 and 6. 4.
On depositing entire amount under the impugned award within eight weeks, execution thereof is to stand stayed. [R.G. AVACHAT, J.] KBP