The G.M.I.D.C, Thr Its Ex. Engineer, Medium Project Division, Osmanabad v. Bhagwan Gundiba Sulakhe (Died) Thr Lrs Dnyandev And ORS
10-CA-5202-2018 delay.odt (1)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 10 CIVIL APPLICATION NO. 5202 OF 2018 IN FAST/1175/2018 THE G.M.I.D.C. THR ITS EX. ENGINEER, MEDIUM PROJECT DIVISION OSMANABAD
VERSUS
BHAGWAN GUNDIBA SULAKHE (DIED) THR LRS DNYANDEV AND ORS ...
Advocate for Applicant : Mr. H.T. Gaikwad AGP for Respondents/State : Mr. A.M.Phule Advocate for Respondent No.1 : Mr. P.K. Deshmukh ...
CORAM : P.R. BORA, J.
DATED : 08th OCTOBER, 2018.
PER COURT:- .
Heard Shri Gaikwad, the learned counsel appearing for the applicant and Shri P.K. Deshmukh, the learned counsel appearing for the respondents i.e. original claimants and Shri Phule, the learned AGP appearing for respondent-State.
2.
The learned counsel for the claimants has not disputed the reasons as are assigned by the acquiring body in justification of the delay caused. Hence, the following order:
ORDER
i) The delay of 920 days caused in filing the appeal is condoned. The appeal be
10-CA-5202-2018 delay.odt (2) registered in accordance with law.
ii) The civil application for condonation of delay stands disposed of.
iii) On registration of the appeal, issue notice to the respondents, returnable on 22.11.2018. Shri P.K. Deshmukh waives notice for respondents-original claimants. Shri Phule, the learned AGP waives notice for respondent nos. 6 and
7. Service complete.
iv) List the appeal for further consideration on 22.11.2018.
(P.R. BORA, J.) Mujaheed//