M.I.D.C. Thr Its Regional Manager At Latur v. Hariram Shivram Shelke And ANR
1 CA 1367 of 2016
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 971 CIVIL APPLICATION NO. 1367 OF 2016 IN FIRST APPEAL STAMP NO.1272 OF 2016 ---- The Maharashtra Industrial Development Corporation, Latur. .. Applicant.
Versus
Hariram Shivram Shelke And Another.
.. Respondents.
---- Shri. S.S. Dande, Advocate, for applicant.
Shri. A.N. Irpatgire, Advocate, for respondent No.1.
Shri. A.R. Kale, Assistant Government Pleader, for respondent No.2.
---- Coram: T.V. NALAWADE & SANGITRAO S. PATIL, JJ.
Date: 2 March 2017 ORDER:
The application is filed for condonation of delay caused in filing first appeal by the acquiring body. Both the sides are heard. Delay of 62 days is caused in filing the appeal.
2) In view of the contentions made in the applications and the submissions made this Court
2 CA 1367 of 2016 holds that sufficient cause is shown. The civil application is allowed. Delay is condoned. The appeal is admitted. Notice in the appeal is waived by learned counsel appearing for the original claimant.
Sd/- Sd/- (SANGITRAO S. PATIL, J.) (T.V. NALAWADE, J.) rsl