M/S Zambad Infrastructure Ltd. A Company Registered As Per The Campanies Act 1956 Thr Its Director v. The State Of Maharashtra And Others
1 wp 1493.22
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD WRIT PETITION NO. 1493 OF 2022 M/s Zambad Infrastructure Ltd. A Company Registered as per the Companies Act, 1956 through its Director .. Petitioner
Versus
The State of Maharashtra and others .. Respondents Shri Shubham S. Khoche, Advocate for the Petitioner. Shri S. B. Yawalkar, Addl.G.P. for the Respondent No. 1. CORAM :
S. V. GANGAPURWALA AND S. G. DIGE, JJ.
DATE :
01ST FEBRUARY, 2022.
FINAL ORDER :
.
The learned counsel for the petitioner submits that, application give by the petitioner for refund of the amount below Exhibit 329 in R. P. No. 31 of 2007 is not yet decided by the Recovery Officer, Debt Recovery Tribunal, Aurangabad, though more than two years have lapsed. The petitioner further seeks directions to the respondent No. 2 to refund the amount with interest within stipulated period.
2.
It appears that, the application filed by the petitioner below Exhibit 329 is pending before the Recovery Officer. The recovery officer shall after hearing all the parties concerned decide the application of the petitioner for refund of amount on
2 wp 1493.22 its own merits, in accordance with law, expeditiously and preferably within a period of six (06) months from today. 3.
In the light of the above, the writ petition is disposed of. No costs.
[S. G. DIGE, J.] [S. V. GANGAPURWALA, J.] bsb/Feb. 22