Hari Dnyanoba Ubale v. The State Of Maharashtra Through Its Secretary And Others
{1} 937 sr.no..odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD WRIT PETITION NO.518 OF 2023 HARI DNYANOBA UBALE
VERSUS
THE STATE OF MAHARASHTRA THROUGH ITS SECRETARY AND OTHERS ...
Advocate for Petitioner : Mr. Vishal A. Bagal Additinoal GP for Respondents No.1 and 2: Mr. S.B. Yawalkar. Advocate for respondent No.3 : Mr. A.S. Bajaj. CORAM : MANGESH S. PATIL & S.G. CHAPALGAONKAR, JJ.
DATE : 13 JANUARY 2023 P.C.:- 1.
Heard.
2.
The petitioner is approaching this Court merely for a relief on account of pendency of his application with the respondent No.2 - Collector, purportedly filed under Rule 3(1) of the Maharashtra Electricity Works of Licence Rules, 2012, which he had filed on 09.02.2022.
3.
The learned Advocate for respondent No.3 - MSEDCL - Mr. Bajaj appears suo motu. The petitioner is not seeking relief against it. 4.
We dispose of the writ petition by directing the respondent No.2 - Collector to pass appropriate orders on the petitioner's application (Exhibit A) dated 09.02.2022, as expeditiously as possible and in any case, within a period of sixteen weeks.
[S.G. CHAPALGAONKAR] [MANGESH S. PATIL] JUDGE JUDGE grt/-