Balaji Kondiba Jamdade And ORS v. The Executive Engineer, Upper Penganga Project Division No.6, Nanded Under Gmidc Aurangabad And ORS
ca4363-18 drp
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 4363 OF 2018 IN FIRST APPEAL STAMP NO.26253 OF 2016 Balaji Kondiba Jamdade and Others APPLICANTS
VERSUS
The Executive Engineer, Upper Penganga Project Div. No.6, Nanded and Others RESPONDENTS .......
Mr. Shrinivas H. Panchal, Advocate for applicants Mr. B. R. Surwase, Advocate for respondents .......
[CORAM : SUNIL P. DESHMUKH, J.] DATE : 28 th MARCH, 2018 ORDER :
1.
This is an application moved by the claimants to withdraw the amount deposited in this court by the acquiring body. 2.
Entitlement of the applicants cannot be said to be any longer in dispute in view of withdrawal of the matter by the appellant / acquiring body.
3.
In the circumstances, applicants would be legitimately able to withdraw the amount deposited in this court, pursuant to their claim as accepted by the acquiring body.
4.
As such, the application is allowed in terms of prayer clause "B" and is disposed of.
[SUNIL P. DESHMUKH, J.] drp/ca4363-18