Morya Infrastructure Private Limited Through Its Director Bhaskar Tukaram Waghmare And Others v. Chief Engineer Public Region Aurangabad And Others
1 43-arbappln7-15.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD ARBITRATION APPLICATION NO.2 OF 2015 MORYA INFRASTRUCTURE PRIVATE LIMITED THROUGH ITS DIRECTOR BHASKAR TUKARAM WAGHMARE
VERSUS
CHIEF ENGINEER PUBLIC REGION AURANGABAD AND OTHERS -- Mr.L.D.Vakil, advocate i/b.
Mr.S.M.Sangale, advocate for applicant Mr.S.P.Dound, AGP for respondent nos.1 to 4 -- CORAM : M.T. JOSHI, J.
DATE : MARCH 02, 2015 PER COURT :
Heard both sides.
2] Learned A.G.P. files on record the communication received by him from the respondents, dated 18th February, 2015. The same is accepted on record and marked as "X" for the purpose of identification.
3] The communication would show that now, the respondents have appointed an Arbitrator. Though
2 43-arbappln7-15.odt it was desirable that the respondents should have appointed an Arbitrator in view of the agreement, it is only after filing of the present application, the Arbitrator is appointed.
4] In the circumstances, by recording displeasure of this Court, present application is disposed, as the Arbitrator is appointed.
[M.T. JOSHI, J.] kbp