The New India Assurance Co. Ltd., Thr Its Branch Manager, Aurangabad v. Shakilabee W/O Shaikh Shariff And ORS
942-CA-4530-2018 (D)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 942 CIVIL APPLICATION NO. 4530 OF 2018 IN FAST/2525/2018 THE NEW INDIA ASSURANCE CO. LTD., THR ITS BRANCH MANAGER, AURANGABAD AND ORS
VERSUS
SHAKILABEE W/O SHAIKH SHARIFF AND ORS ...
Advocate for Applicant : Mr. A.S. Usmanpurkar Advocate for Respondents No.1 to 4 : Mr. Quadri Taher Ali ....
CORAM : V.L. ACHLIYA, J.
DATED : 20th JULY, 2018 PER COURT:- 1.
Heard. Perused the application.
2.
The applicant has preferred this application seeking condonation of 7 days delay in filing the appeal. 3.
Considering the cause assigned in the light of unchallenged pleadings of the application, I am of the view that sufficient cause has been made out to condone the delay. Hence, the following order:
ORDER
(A) The delay is condoned.
(B) Appeal be registered.
(C) Civil Application be marked as disposed of. ( V.L. ACHLIYA ) JUDGE SPR