The Executive Engineer Nimna Dhudhana Project Selu v. The State Of Maharashtra And Others
2024:BHC-AUG:5274 47.odt
IN THE NATIONAL LOK ADALAT PRESIDED OVER BY
HON'BLE SHRI JUSTICE S. G. MEHARE, J.
HELD ON 03rd March, 2024, AT HIGH COURT LEGAL SERVICES SUB-COMMITTEE AT AURANGABAD FIRST APPEAL NO.221 OF 2016 WITH FA/223/2016 WITH X-OBJST/27738/2016 IN FA/221/2016 WITH X-OBJST/27752/2016 IN FA/223/2016 THE EXECUTIVE ENGINEER NIMNA DHUDHANA PROJECT
VERSUS
THE STATE OF MAHARASHTRA AND ANOTHER ...
Mr. More Kumar Gaurav h/f Mr. A.B. Kale, Advocate for respondent no.3.
Mr. S.V. Hange, AGP for the State.
Mr. S.C. Arora, Advocate for respondent/acquiring body.
O R D E R
1.
The claimants and the acquiring body have voluntarily arrived at the settlement and filed the compromise terms which are taken on record. The terms of the compromise are duly verified by the claimants and the acquiring body which are identified by their respective counsels.
2.
Hence, both appeals stand disposed of in terms of the compromise.
3.
The decree be drawn up accordingly.
4.
Court fee refund certificate, if required be issued to the parties as per rules.
5.
The acquiring body shall deposit the award amount with
47.odt the learned Reference Court as agreed. Upon such deposit, the claimants are entitled to withdraw the same.
6.
Any undertaking or security if given by the claimants towards earlier withdrawal stands discharged. 7.
Since the parties have settled the dispute, nothing remains in the cross objection. The cross objections stands disposed of.
(AJIT B. KADETHANKAR) (V. B. MANTRI ) ( S. G. MEHARE, J. ) Advocate District Judge (Retd.) Head of the Panel Member Member Date : 03.03.2024.
Place : Aurangabad.
Mujaheed//