Executive Engineer Irrigation Project Strengthening Division Omerga v. Dattatraya Dhhula Kokare And Others
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
BENCH AT AURANGABAD CIVIL APPLICATION NO.3350 OF 2014 IN FIRST APPEAL ST.NO.2811 OF 2014 Executive Engineer, Irrigation Project Strengthening Division, Omerga ..Applicant
Versus
Dattatraya Dhhula Kokare and ors.
..Respondents Mr S.G. Sangle, Advocate for applicant Mr S.P. Daund, A.G.P. for respondents 3 and 4 CORAM : N.W. SAMBRE, J.
DATE : 20th March 2015 PER COURT 1.
The non-applicants No.1 and 2 are served. None appears. 2.
There is delay of 650 days caused in preferring the present first appeal.
3.
For the reasons stated in the application, delay is condoned subject to payment of costs of Rs.2,000/-; to be paid to High Court Bar Association's Library, Aurangabad within a period of eight weeks from today.
4.
Civil Application stands allowed accordingly. ( N.W. SAMBRE, J.) vvr