IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD 52 CIVIL APPLICATION NO. 1467 OF 2025 IN FAST/3477/2025 SUSHANT TUKARAM DHAWALE

VERSUS

EXECUTIVE ENGINEER, MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTED AND ANR ...

Mr. Deshmukh Mohit R., Advocate for Applicant Mr. U. S. Malte, Advocate for Respondent No.1 ....

CORAM : S. G. CHAPALGAONKAR, J.

DATE : 07.05.2025 PER COURT :- .

Heard Mr. Deshmukh learned Advocate appearing for applicant.

2.

By this application, applicant seeks to condone the delay of (01) day caused in filing appeal.

3.

Perused application and reasons as stated therein. Sufficient cause is made out to condone delay. Hence, following order:

::ORDER::

a.

Civil Application is allowed and disposed of. b.

Delay of 01 day caused in filing appeal is hereby condoned.

c.

Appeal be registered.

[ S. G. CHAPALGAONKAR, J. ] HRJadhav