G.M.I.D.C. Thr The Executive Engineer, Latur And ANR v. Shivdas Sangramappa Murke Thr Gpa Rajeshwar S Murke And ANR
26.CA.dly.14019.17.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 26 CIVIL APPLICATION NO.14019 OF 2017 IN FAST/3714/2017 WITH CA/14022/2017 IN FAST/3780/2017 WITH CA/14024/2017 IN FAST/3777/2017 WITH CA/14028/2017 IN FAST/3795/2017 WITH CA/14031/2017 IN FAST/3786/2017 WITH CA/14033/2017 IN FAST/3789/2017 WITH CA/14035/2017 IN FAST/3783/2017 G.M.I.D.C. THR THE EXECUTIVE ENGINEER, LATUR AND ANR
VERSUS
CHANDAR DEORAO JADHAV (DIED) LRS BALAJI AND ORS ...
CORAM
: MANGESH S. PATIL, J.
DATE : .17.12.2019 PER COURT :
There is a delay of 2146 days for the acquiring body to prefer these appeals.
2.
The respondent claimants have been duly served but have not appeared and the grounds mentioned in the applications have gone without any demur.
3.
For the reasons mentioned in the applications, the delays are condoned. Issue notice after registration of the appeal returnable within 12 weeks.
(MANGESH S. PATIL, J.) habeeb 1/1