The Chief Engineer (Construction) Central Railway, Mumbai And ANR v. Manmanth Babarao Chikte (Died) Thr Lrs Anusaya And ORS
2707.20CA
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 952 CIVIL APPLICATION NO.2707 OF 2020 IN FIRST APPEAL STAMP NO.3863 OF 2020 THE CHIEF ENGINEER (CONSTRUCTION) CENTRAL RAILWAY, MUMBAI & ANOTHER
VERSUS
MANMANTH BABARAO CHIKTE (DIED) THROUGH L.Rs.ANUSAYA (DIED) & OTHERS ...
Advocate for applicants : Mr.M.N.Navandar Advocate for respondents : Mr.S.S.Halkude AGP for Respondent-State : Mrs.D.S.Jape ...
CORAM : S.G.DIGE, J.
DATE : 13.09.2022 P.C. :
1] Heard the learned counsel for the applicants, learned AGP for respondent-State and the learned counsel for respondents.
2] Considering the submissions of all learned counsel and the reasons mentioned in the application, delay of 191 days for filing First Appeal is condoned. Appeal be registered subject to removal of office objections, if any. 3] Civil Application is disposed of accordingly. [S.G.DIGE] JUDGE DDC