The Executive Engineer, Irrigation Project Majbutikaran Div. Omerga And ORS v. Ramdas Digambar Khirsagar And ANR
1 931-CA-7173-18-S
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 931 CIVIL APPLICATION NO. 7173 OF 2018 IN FAST/3943/2018 THE EXE.ENGINEER, IRRIGATION PRO.MAJBUTIKARAN DIV., OMERGA & ORS
VERSUS
RAMDAS DIGAMBAR KHIRSAGAR AND ANR.
...
Advocate for Applicants : Mr. Gulab B. Rajale. AGP for Respondent State : Mr. A. M. Phule.
Advocate for Respondents-original claimants : Mr. R. V. Naiknavare. ...
CORAM : K.K. SONAWANE, J.
DATED : 15th JUNE, 2018.
Order :- 1.
Heard learned counsel for applicants-appellants. 2.
Perused the application and other relevant documents. 3.
There shall be stay to the execution and operation of the impugned Judgment and Award, passed by the learned Reference Court in Land Acquisition Reference, on condition that applicants/ appellants shall deposit the entire amount of compensation pursuant to award along with interest accrued thereon in this court within a period of six weeks from today. Failure to which, the stay granted shall stand vacated automatically without further reference to the Court with liberty to the respondents/original claimants to avail the recourse of law for execution of the award within ambit of law. 4.
Accordingly, civil application stands disposed of. [ K. K. SONAWANE ] JUDGE rrd.