The Executive Engineer Mid Jalna v. Subhash S/O Bapurao Mhaske And ORS
2025:BHC-AUG:1641 (1) 65-ca-3060-2024.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 3060 OF 2024 IN FAST/3650/2024 THE EXECUTIVE ENGINEER MID JALNA
VERSUS
SUBHASH S/O BAPURAO MHASKE AND ORS ...
Mrs. Surekha G. Chincholkar, Advocate for Applicant. Mr. D. B. Bhange, AGP for Respondents-State.
...
CORAM : S. G. CHAPALGAONKAR, J.
DATED : 17th JANUARY, 2025.
P.C.:- 1.
By this application, applicant seeks to condone delay of 1599 days caused in filing Appeal.
2.
The applicant is original claimant in Land Acquisition Reference No.164/2011, that has been decided by Reference Court on 15.06.2019.
3.
Perusal of the application shows that delay is attributed to the administrative reasons.
4.
Although respondent nos.1 to 3 are served with notice of this application, reasons as stated in the application are not controverted by filing affidavit.
5.
In that view of the matter, case is made out to condone the delay. Hence, following order:
ORDER
a.
Civil Application is allowed.
(2) 65-ca-3060-2024.odt b.
Delay of 1599 days caused in filing Appeal is hereby condoned.
c.
Appeal be registered.
(S. G. CHAPALGAONKAR) JUDGE Devendra/January-2025