Bombay High CourtCA/8782/2016disposed offdismissed for default

The Executive Engineer, Minor Irrigation Division, Osmanabad v. Sopan Dattu Dawakare And ORS

2017-06-21Hon'Ble Shri Justice P.R. Bora1 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD (1) CA NO.8782/2016gr 11 CIVIL APPLICATION NO. 8782 OF 2016 IN FAST/5012/2016 WITH CA/8784/2016 IN FAST NO.5057/2016 THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD

VERSUS

SOPAN DATTU DAWAKARE AND ORS ...

Advocate for Applicant : Mr.Sonwalkar Vilas R. AGP for Respondent State: Mr. S.P.Sonpawale ...

CORAM : P.R. BORA, J.

Dated: June 21, 2017 ...

PER COURT :- 1.

C.A.No.8784/2016 is not on Board. Taken on Board. 2.

Delay of 994 days has occurred in preferring the appeals. Respondents / original claimants though are duly served, have not entered their appearance in the matter. Learned A.G.P. appears for respondent nos. 3 and 4 i.e. the State. Learned Counsel submitted that in making procedural compliances, the delay was caused. Considering the explanation as provided by the acquiring body, the delay is condoned. The applications are allowed. The appeals be registered in accordance with law and be immediately placed for the purpose of admission. ( P.R. BORA, J. ) ...

agp/-