IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD.

916 CIVIL APPLICATION NO. 4790 OF 2017 IN FAST/15868/2016 THE EXE ENGINEER, NIMNA DUDHANA PROJECT DIV SELU,(JAIKWADI CONS.

PROJECT DIV NO.7 PARBHANI) & Ors .. Applicants

VERSUS

DASHRATH PIRAJI KHOSE .. Respondent ......

Advocate for Applicants :

Mr. R. C. Patil .....

CORAM : P.R. BORA, J.

Dated: July 04, 2017 PER COURT :

.

For the reasons stated in the application, the application is allowed in terms of prayer clauses 'A' and 'B'. Delay caused in filing the application is condoned. Abatement, if any, stands set aside. The legal heirs of deceased respondent no.1 be taken on record within two weeks.

2.

Civil Application stands disposed of.

( P.R. BORA, J. ) ggp