Paris Ispat Pvt Ltd Through Its Director Amit Vallabharay Pandit v. The Chief Engineer Mumbai And Others
WP-2019.16
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD WRIT PETITION NO. 2019 OF 2016 Paris Ispat Pvt. Ltd.
...PETITIONER versus The Chief Engineer ( Commercial) and others ...RESPONDENTS .....
Mr. Abhijit S. More, Advocate for petitioner Mr. A.S. Bajaj, Advocate for respondent No. 2 .....
CORAM : S. V. GANGAPURWALA AND K.K. SONAWANE, JJ.
DATED : 31st MARCH, 2016.
Order :-
1. Mr. A.S. Bajaj, learned counsel for respondent No. 2, on instructions, submits that Chief Engineer, (Commercial) MSEDCL would take decision upon the claim made by the petitioner within a period of two weeks from today.
2.
In the light of that, writ petition stands disposed of. No costs.
3. If any of the party is aggrieved by the decision, they are entitled to take steps in accordance with law. Interim order passed by this court under order dated 22nd February, 2016 shall continue for a period of two weeks from today. Needless to state that after expiry of two weeks period, the same would come to an end.
Sd/- Sd/- [ K. K. SONAWANE, J.] [S. V. GANGAPURWALA, J.] MTK