Rohini Rajendra Jondhale v. The United India Insurance Co. Ltd., Thr Its Div. Manager, Ahmednagar And ANR
2024:BHC-AUG:3346 {1} 956 sr.no..odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 956 CIVIL APPLICATION NO. 7725 OF 2022 IN FAST/5400/2020 Rohini Rajendra Jondhale ....Applicant
VERSUS
The United India Insurance Co. Ltd., Thr Its Div. Manager, Ahmednagar And Anr .....Respondent .....
Advocate for Applicant : Mr. Shaikh Majit S And Y.k. Shaikh Advocate for Respondent No.1 Mr. Deshmukh Mohit R. CORAM : S.G. CHAPALGAONKAR, J.
DATE : 13TH FEBRUARY, 2024.
ORDER :- By this application, the applicant seeks to condone the delay of 94 days caused in filing the first appeal against the judgment and award dated 31/7/2019 passed by Motor Accidents Claim Tribunal, Sangamner in MACP No. 64 of 2011.
2.
Having considered the reasons as stated in para. Nos. 2 to 6 of the application, it can be gathered that there are sufficient grounds to condone the delay. Resultantly, the application deserves to be allowed. Hence, the order :-
{2} 956 sr.no..odt
O R D E R
[I] Civil application is allowed.
[ii] Delay of 94 days caused in filing the appeal is condoned [iii] Appeal be registered.
[iv] On registration of appeal, issue notice to respondents returnable on 26th March, 2024.
[v] Call for R. & P.
[S.G. CHAPALGAONKAR] JUDGE grt/-