The Executive Engineer, Minor Irrigation Division, Usmanabad v. The State Of Maharashtra And Others
1 20-ca4823-13 and ors.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CA/4823/2013 IN FAST/5827/2013 WITH CA/4825/2013 IN FAST/5862/2013 WITH CA/4827/2013 IN FAST/5865/2013 WITH CA/4829/2013 IN FAST/5868/2013 THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD
VERSUS
THE STATE OF MAHARASHTRA AND OTHERS -- Mr.S.G.Bhalerao, advocate for applicants Mr.S.M.Joshi, AGP for respondents 1 and 2 Mr.B.K.Pawar, advocate for respondent no.3 -- CORAM : M.T. JOSHI, J.
DATE : FEBRUARY 11, 2015 PER COURT :
Heard both sides.
2] Learned counsel for the applicants/appellants submits that as the matter was processed at different levels for obtaining sanction to file the appeals, the delay has occurred in filing the appeals.
2 20-ca4823-13 and ors.odt 3] I am satisfied that sufficient reasons are made out for condonation of delay. Delay is, therefore, condoned.
The applications are allowed.
[M.T. JOSHI, J.] kbp