The Executive Engineer Minor Irrigation Division (Local Sector) Jalna And ORS v. Narayan Bhaurao Uddange
2025:BHC-AUG:9159 (1) 49-ca-1004-2025.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 1004 OF 2025 IN FAST/5288/2024 THE EXECUTIVE ENGINEER MINOR IRRIGATION DIVISION (LOCAL SECTOR) JALNA AND ORS
VERSUS
NARAYAN BHAURAO UDDANGE ...
Mr. Hemant U. Dhage, Advocate for Applicants. Mr. D. M. Pingale, Advocate for Respondent Nos.1 and 2. ...
CORAM : S. G. CHAPALGAONKAR, J.
DATED : 27th MARCH, 2025.
P.C.:- 1.
Heard learned Advocates appearing for respective parties. 2.
By this application, applicants seek to condone delay of 634 days caused in fling Appeal.
3.
Perused application and reasons as stated therein. Delay appears to have been occasioned on account of administrative exigency. The applicants have not derived any advantage by making such delay. The contents in the application are not controverted by filing affidavit-in-reply. Hence, sufficient cause is made out to condone delay. Hence, following order:
ORDER
a.
Civil Application is allowed.
b.
Delay of 634 days caused in filing Appeal is hereby condoned. c.
Appeal be registered subject.
(S. G. CHAPALGAONKAR) JUDGE Devendra/March-2025