IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO.3540 OF 2016 IN ARBITRATION APPEAL NO. 7 OF 2016 WITH CIVIL APPLICATION NO.3548 OF 2016 IN ARBITRATION APPEAL NO. 8 OF 2016 WITH CIVIL APPLICATION NO.3543 OF 2016 IN ARBITRATION APPEAL NO. 9 OF 2016 The Executive Engineer, under GMIDC, Aurangabad ..APPLICANT

VERSUS

M/s. M. D. Parmar ..RESPONDENT Mr B. R. Surwase, Advocate for applicant Mr Amol Gawali, Advocate for respondent WITH CIVIL APPLICATION NO.3602 OF 2017 IN ARBITRATION APPEAL NO. 7 OF 2016 WITH CIVIL APPLICATION NO.3603 OF 2017 IN ARBITRATION APPEAL NO. 8 OF 2016 WITH CIVIL APPLICATION NO.3605 OF 2017 IN ARBITRATION APPEAL NO. 9 OF 2016

(2) M/s. M. D. Parmar ..APPLICANT

VERSUS

The Executive Engineer, under GMIDC, Aurangabad ..RESPONDENT Mr Amol Gawali, Advocate for applicant;

Mr B. R. Surwase, Advocate for respondent CORAM : NITIN W. SAMBRE, J.

DATE : 5th OCTOBER, 2017 ORAL ORDER :

The amount deposited by the present applicant be invested in fixed deposit in nationalized bank, initially for a period of three years. The interest accrued thereon be paid to the respondent after every six months, subject to applicant furnishing an undertaking to this Court within two weeks that in case, present appeals are allowed, he shall re-deposit the said amount with interest, as is paid by the bank, of which he is beneficiary.

2.

There shall be stay to the execution.

(3) 3.

With above observations, all civil applications stand disposed of.

( NITIN W. SAMBRE, J.) Tupe