IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD (1) CA NO.3628 OF 2012gr 5 CIVIL APPLICATION NO. 3628 OF 2012 IN FAST/6214/2012 WITH CA/3629/2012 IN FAST/6214/2012 WITH CA/3630/2012 IN FAST/6279/2012 WITH CA/3631/2012 IN FAST/6279/2012 WITH CA/3632/2012 IN FAST/6274/2012 WITH CA/3633/2012 IN FAST/6274/2012 EXECUTIVE ENGINEER, IRRIGATION PROJECT STRENGTHENING DIVISION OMERGA

VERSUS

SHARNAPPA JETINGA DHANGAR AND ORS ...

Advocate for Applicant :Mr. Sangle Shirish G. AGP for Respondent State:Mr.S.P.Deshmukh ...

CORAM : P.R. BORA, J.

Dated: August 26, 2016 ...

PER COURT :- 1.

Heard Shri Sangle, learned Counsel appearing for the acquiring body, Shri Deshmukh, learned A.G.P. appearing for the respondent State and the Special Land Acquisition Officer. The original claimants, though are duly served, have not entered their appearance. 2.

Delay of 264 days has occurred in filing the present appeals. For the reasons stated in the AGP/-

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD (2) CA NO.3628 OF 2012gr applications which, according to me, are just and sufficient, the delay is condoned. Civil Applications for condonation of delay stand disposed of.

3.

The appeals be registered in accordance with law.

4.

Issue notice to the respondents in the applications for stay returnable on 7.10.2016. ( P.R. BORA, J. ) ...

AGP/-