IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 969 CIVIL APPLICATION NO.6646 OF 2018 IN FAST/6323/2018 EX. ENGINEER, VISHNUPURI PROJECT DIV. NO. NANDED NOW LENDI PRO. DIV. DEGLOOR UNDER G.M.I.D.C. AND ORS

VERSUS

RAMESHWAR MADHAVRAO NUCCHE ...

Advocate for Applicants : Mr. Surwase B.R.

Advocate for Respondent : Mr. G.N. Chincholkar ...

CORAM : SMT. VIBHA KANKANWADI, J.

DATE : 13th SEPTEMBER, 2019.

ORDER :

.

Present application has been filed by the acquiring body for getting the delay of 2417 days condoned in filing first appeal. The acquiring body intends to challenge the judgment and award passed by the learned reference Court.

2.

The learned Advocate appearing for the respondent/original claimant has strong objection to allow the application on the ground that whatever ground has been stated in the application is absolutely not sufficient and reasonable. It is stated that there is huge and inordinate delay.

969 (delay).doc 3.

Though the delay is huge, it has been tried to be explained by the acquiring body in paragraph Nos. 3 to 5 and therefore, the delay stands condoned.

4.

Civil Application stands allowed and disposed of accordingly. 5.

Registry to verify and register the first appeal and place it for further consideration on 13.01.2020.

(SMT. VIBHA KANKANWADI, J.) SCM