The Ex. Engineer, Minor Irrigation Division, Jalgaon And ANR v. Ziparu Madhav Chaudhari And ORS
(1) ca3447.21
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 947 CIVIL APPLICATION NO.3447 OF 2021 IN FAST/38357/2019 WITH CA/3448/2021 IN FAST/38350/2019 THE EX. ENGINEER, MINOR IRRIGATION DIVISION, JALGAON AND ANR
VERSUS
ZIPARU MADHAV CHAUDHARI AND ORS Mr. Ajay D. Pawar, Advocate for the applicants Mr. S. B. Pulkundwar, AGP for the respondent/State Mr. Vinod P. Patil, Advocate for the respondent Nos. 1 to 6 CORAM :
N. J. JAMADAR, J.
DATE :
12-03-2021 P. C.
.
Heard learned counsel for the applicants and respondent-original claimant.
2.
These applications are preferred seeking extension of time to deposit the amount in terms of the order passed by this court on 02-12-2020 whereby 12 weeks time was granted to deposit the amount in terms of the award passed by the Reference Court in LAR Nos.722/2010 & 723/2010 dated 14-02-2019. 3.
Learned counsel for the applicants submits that in view
(2) ca3447.21 of the situation which arose on account of Covid-19 pendamic the applicants could not deposit the amount of compensation within the stipulated period.
4.
For the reasons assigned in the applications and in the light of submission, by way of final indulgence, six weeks time is granted to the applicants to deposit the entire amount of compensation as ordered by this court by order dated 02-12-2020. In the event of default, the claimants would be at liberty to execute the award.
5.
The civil applications stand disposed of.
[ N. J. JAMADAR, J. ] VishalK/ca3447.21