← Library
Bombay High CourtCA/3083/2021delay condonatedrejected

Babu Limba Veer Died His Lrs Hanumant Babu Veer And ORS v. The Executive Engineer, Lift Irrigation Division, Osmanabad And ORS

2021-10-21Hon'Ble Shri Justice R. G. Avachat1 pages

IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO.3083 OF 2021 IN CROSS-OBJECTION (ST.) NO.6464 OF 2020 IN FIRST APPEAL NO.4757 OF 2017 Babu Limba Veer, Died L.rs.

Hanumant s/o Babu Veer & ors.

... APPLICANTS

VERSUS

The Executive Engineer, Lift Irrigation, Osmanabad & ors.

... RESPONDENTS .......

Mr. R.A. Deshmukh, Advocate for applicants Mr. P.M. Kulkarni, A.G.P. for State .......

CORAM :

R. G. AVACHAT, J.

DATE :

21st OCTOBER, 2021 PER COURT :

There is delay of 572 days in filing the CrossObjection. Moreover, there is also delay of little over one and half year for seeking circulation of this application. For the reasons given in the application, the application is allowed. Delay condoned on condition that the applicant/ claimant shall not be entitled for component of interest for the delayed period of 572 days plus delay from 11/2/2020 to the date of this order.

( R. G. AVACHAT ) JUDGE fmp/-