Executive Engineer Latur Minor Irrigation Division Latur Under G.M.I.D.C. Aurangabad And Another v. Ashwini Dilip Kulkarni

2019-07-05Hon'Ble Smt. Justice Vibha Kankanwadi2 pages

1066-ca-4149-15.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 1066 CIVIL APPLICATION NO.4149 OF 2015 IN FAST/6695/2015 WITH CA/4151/2015 IN FAST/6569/2015 WITH CA/4153/2015 IN FAST/6700/2015 WITH CA/4156/2015 IN FAST/6705/2015 EXECUTIVE ENGINEER LATUR MNOR IRRIGATION DIVISION LATUR UNDER G.M.I.D.C. AURANGA

VERSUS

ARCHANA DILIP KULKARNI ...

Advocate for Applicant : Mr. Surwase B.R.

Advocate for Respondent : Mr. M.L. Dharashive h/f Mr. S.S. Pawar. ...

CORAM : SMT. VIBHA KANKANWADI, J.

DATE : 5th JULY 2019 ORDER :

1.

Present applications have been filed for getting the delay of 960 days in filing First Appeal condoned. The applications have been strongly opposed by the respondent on the ground that the delay of each and every day has not been properly explained. However, taking into consideration the reasons, those have been given, which are satisfactory, the delay is hereby condoned.

2.

Learned Advocate for the applicant makes a statement that the amount would be deposited within one month which was in fact already directed to be deposited in this Court as per the order passed on the applications for stay. Since the time has already been lapsed which

1066-ca-4149-15.doc was granted on 27-02-2017, the statement is made that now the amount would be made available. This Court hopes that the appellants shall perform as per the instructions.

3.

Civil Applications stand disposed of accordingly. 4.

Registry to verify and register the First Appeals and place it for further consideration on 29-8-2019.

( Smt. Vibha Kankanwadi, J. ) Shubham/