Executive Engineer, Minor Irrigation Division, Osmanabad v. Mahiphathi Govindrao Doiphode And ANR
997-ca-6013-19.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO.6013 OF 2019 IN FIRST APPEAL (ST) NO.6499 OF 2019 EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD
VERSUS
MAHIPHATHI GOVINDRAO DOIPHODE AND ANR ...
Mr. V.C. Solshe, Advocate for Applicant.
Mr. R.B. Bagul, AGP for Respondents/State.
...
CORAM : SMT. VIBHA KANKANWADI, J.
DATE : 2nd AUGUST, 2019.
ORDER :
.
Present application has been filed for getting the delay of 2207 days condoned in filing first appeal. The acquiring body intends to challenge the judgment and award passed by the learned reference Court. Learned AGP representing respondent No.2 has no objection. Though the original claimant is represented by learned Advocate, he is absent. Under such circumstance, whatever the reasons mentioned in the application have gone unchallenged, therefore, delay stands condoned. 02.
Civil Application stands allowed and disposed of accordingly.
997-ca-6013-19.doc 03.
Registry to verify and register the first appeal and place it for further consideration on 11.12.2019. 04.
Time to deposit the amount as directed in the stay application is extended by six weeks only.
05.
If the compliance is not made, then it shall be treated that there is no stay.
( Smt. Vibha Kankanwadi, J. ) Shubham/