The Executive Engineer, Medium Project v. The State Of Mah Thr Collector
1 5838.2012CA.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY.
BENCH AT AURANGABAD.
942 CIVIL APPLICATION NO. 5838/2012 IN FAST/6760/2012 WITH CA/5840/2012 IN FAST/6795/2012 CA/5842/2012 IN FAST/6799/2012 CA/5844/2012 IN FAST/6789/2012 CA/5846/2012 IN FAST/6792/2012 CA/5848/2012 IN FAST/6785/2012 CA/5850/2012 IN FAST/6803/2012 THE EXECUTIVE ENGINEER, MEDIUM PROJECT ..Applicant
VERSUS
THE STATE OF MAH THR COLLECTOR ..Respondent ...
Advocate for Applicant : Shri S.K. Rahane ...
CORAM : P.R. BORA, J.
Dated: September 05, 2018 PER COURT :
1.
Heard Shri Rahane, the learned Counsel appearing for the applicant-Acquiring Body. Learned Counsel submitted that, he is in receipt of the cheque for the amount of Rs.16,92,864/-, which is consolidated amount of compensation in respect of all 7 matters. The learned Counsel has sought permission for depositing the said amount. Though the time stipulated for deposit of the amount had expired long back, I am inclined to extend the said period and permit the Acquiring Body to deposit the said amount. Hence, the following order.
2 5838.2012CA.doc
ORDER
(i) Time to deposit the amount of compensation stands extended by one week.
(ii) The Registry to accept the cheque for the amount of Rs.16,92,864/-.
(iii) All Civil Applications for stay stand disposed of. (iv) Authenticated Copy be provided to the parties to act upon. (P.R. BORA, J.) ggp