Bombay High CourtCA/5284/2018disposed offdismissed for default

The G.M.I.D.C., Thr The Ex. Director And The Ex. Engineer, M.P. Vadala Project, Osmanabad v. Bhagwan Subrao Shelke And ORS

2019-03-19Hon'Ble Shri Justice Sunil K. Kotwal2 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 915 CIVIL APPLICATION NO.5284 OF 2018 IN FA/2676/2018 THE G.M.I.D.C., THR THE EX. DIRECTOR AND THE EX. ENGINEER, AND ORS

VERSUS

BHAGWAN SUBRAO SHELKE AND ORS ...

Advocate for Applicant No. 1 : Mr. Anand Chawre AGP for Applicant No. 2 : Mr. R.B.Bagul Advocate for Respondent: Mr. Ingale Vivekanand V. ...

CORAM : SUNIL K.KOTWAL, J.

DATE : 19 th MARCH, 2019 O R D E R :

The Acquiring body today deposited the entire compensation amount as per direction of this Court. Therefore, stay order is confirmed till final hearing of the appeal.

Civil Application is disposed of.

[SUNIL K.KOTWAL, J.] mahajansb/