Executive Engineer, Minor Irrigation Division, Osmanabad v. Banshi Khandu Nangare And ORS
997-ca-6014-19 group (delay).doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 997 CIVIL APPLICATION NO.6015 OF 2019 IN FAST/6812/2019 WITH CA/6017/2019 IN FAST/6785/2019 WITH CA/6019/2019 IN FAST/6816/2019 WITH CA/6021/2019 IN FAST/6804/2019 WITH CA/6023/2019 IN FAST/6839/2019 WITH CA/6025/2019 IN FAST/6796/2019 WITH CA/6027/2019 IN FAST/6833/2019 WITH CA/6029/2019 IN FAST/6809/2019 WITH CA/6031/2019 IN FAST/6827/2019 WITH CA/6033/2019 IN FAST/6790/2019 EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION, OSMANABAD
VERSUS
MAHIPHATHI GOVINDRAO DOIPHODE AND ANR ...
Advocate for Applicant : Mr. Solshe Vinesh C Advocate for Respondents/State : Mr. R.B. Bagul ...
CORAM : SMT. VIBHA KANKANWADI, J.
DATE : 2nd AUGUST, 2019.
ORDER :
.
Present applications have been filed for getting the delay of 2211 days condoned in filing first appeals. The acquiring body intends to challenge the judgment and award passed by the learned reference Court. Learned AGP representing respondents-State has no objection. Though the original claimants are represented by learned Advocate, he is absent. Under such circumstance, the reasons mentioned in the applications have
997-ca-6014-19 group (delay).doc gone unchallenged, therefore, delay stands condoned. 02.
Civil Applications stand allowed and disposed of accordingly.
03.
Registry to verify and register the first appeals and place them for further consideration on 11.12.2019. 04.
Time to deposit the amount as directed in the stay application is extended by six weeks only.
05.
If the compliance is not made, then it shall be treated that there is no stay.
( Smt. Vibha Kankanwadi, J. ) Shubham/