← Library
Bombay High CourtCA/6160/2013admittedallowedgrantedrule absolute

Executive Engineer, Latur Medium Project Division v. Jotiram Tukaram Somwanshi And Others

2016-01-21Hon'Ble Shri Justice T.V. Nalawade2 pages

-:(1):- FARAD CONTINUATION SHEET NO.

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD.

Office Notes, Office Memoranda of Coram, appearance, Court's orders or directions and Registrar's orders.

Court's or Judge's orders.

CIVIL APPLICATION NO. 6160 OF 2013 IN FA/167/2014 EXECUTIVE ENGINEER, LATUR MEDIUM PROJECT DIVISION

VERSUS

JOTIRAM TUKARAM SOMWANSHI AND OTHERS ...

Advocate for Applicant : Mr. Sangle Shirish G. AGP for Respondent : Mr. S. R. Yadav.

Advocate for Respondent: Mr. P. G. Sontakke.

*** CORAM: T. V. NALAWADE, J.

DATED:

21st JANUARY, 2016.

PER COURT:

1.

The application is filed to stay the execution of judgment and Award of Reference Court. Heard learned counsel for the acquiring body. Seen the judgment and Award. Learned counsel for the acquiring body produced a copy of order made in other connected matters. It appears that this Court had given time of 12 weeks for depositing the amount. Copy of the said order is taken on record.

2.

The application is allowed. Stay is granted to the execution of judgment and Award of Reference Court

-:(2):- subject to the condition of depositing entire amount of compensation within twelve weeks from today. If the amount is not deposited within the aforesaid period, it is to be presumed that there is no stay to the execution of judgment and Award.

[T. V. NALAWADE, J.] Dt.21/01/2016.

ans/6160