New India Assurance Company Ltd Through Its Manager v. Gangabai Baliram Nakhate And 5 Others
2025:BHC-AUG:14990 923-CA.3038-24 (delay).odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 923 CIVIL APPLICATION NO. 3038 OF 2024 IN FAST/7876/2024 THE NEW INDIA ASSURANCE COMPNAY LTD THROUGH ITS MANAGER AND ANR
VERSUS
GANGABAI BALIRAM NAKHATE AND ORS ...
Advocate for Applicant/s : Mr. Aniruddha S. Usmanpurkar. Advocate for Respondent/s : Mr. Khadap Rahul Dattoba. ...
CORAM : SHAILESH P. BRAHME, J.
DATE : 13.06.2025 PER COURT :- 1.
Applicants are seeking condonation of delay of 313 days in preferring appeal challenging compensation granted by the Tribunal in M.A.C.P. No.265 of 2019.
2.
Learned counsel for the applicant would press into service grounds enumerated in paragraph Nos.4 to 12 of the application for condoning delay.
3.
Considering the explanation for condonation of delay tendered in the above paragraphs, I do not find that there is no reason to disbelieve the same. There are no malafides on the part of the applicants in preferring appeal belatedly. It is desirable to allow application.
923-CA.3038-24 (delay).odt 4.
Civil application is allowed in terms of prayer clause "B". 5.
Office to register first appeal.
(SHAILESH P. BRAHME, J.) ...
vmk/-