← Library
Bombay High CourtCA/4738/2017disposed offdismissed for default

Ganesh Tolaji Nirval v. Executive Engineer Nimna Dudhana Project, Selu And ORS

2017-06-09Hon'Ble Shri Justice P.R. Bora1 pages

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD 914 CIVIL APPLICATION NO. 4738 OF 2017 IN FAST/18885/2016 GANESH TOLAJI NIRVAL

VERSUS

EXECUTIVE ENGINEER NIMNA DUDHANA PROJECT, SELU AND ORS ...

Advocate for Applicant : Mr. S.S.Randive AGP for Respondent State: Mr. C.V.Dharurkar ...

CORAM : P.R. BORA, J.

Dated: June 09, 2017 ...

PER COURT :- 1.

Heard learned Counsel appearing for the parties. 2.

Having regard to the grounds of objections raised in exception to the impugned Award and the averments in the application for withdrawal of the amount, I deem it appropriate to pass the following order:

ORDER

i) The applicant is permitted to withdraw 50% of the deposited amount on submitting an undertaking that in the event any adverse order is passed against them, he will re-deposit the said amount within four months of passing such order;

ii) Balance 50% amount be invested in Fixed Deposit Receipt of any Nationalized Bank, initially for a period of two years and if so required for further period till disposal of the appeal; iii) Civil Application stands disposed of in above terms. ( P.R. BORA, J. ) ...

agp/-