Sevalal Shikshan Prasarak Mandal Devnagar Tanda Dist Parbhani Theough Its President v. The State Of Maharashtra And Others
wp3574-2016 IN T HE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD WRIT PETITION NO. 3574 OF 2016 (Sevalal Shikshan Prasarak Mandal, Devnagar Tanda through its President Vs. The State of Maharashtra and others) ---- Mr. K.J. Ghute-Patil, Advocate for the Petitioner Mr. V.H. Dighe, A.G.P. for respondents No. 1 to 5 ---- CORAM :
S.S. SHINDE AND SANGITRAO S. PATIL, JJ.
DATE : 6th JUNE, 2016 PER COURT :
1.
Heard.
2.
The limited grievance made in this petition is that though the proposal of the petitioner is pending with respondents No. 4 and 5 to conduct the assessment of the expenditure incurred by the petitioner to run Balakashram for the years 2010-2011 and 2011-2012, the said proposal is not yet acted upon by respondents No. 4 and 5.
3.
We direct respondents No. 4 and 5 to take the decision on the said proposal, if already not taken, on its own merits and after verifying the record maintained
wp3574-2016 by the office of respondents No. 4 and 5, as expeditiously as possible, however, within a period of ten weeks from today and communicate the said decision to the petitioner.
4.
The writ petition is disposed of on above terms. The parties to act on authenticated copy of this order.
[SANGITRAO S. PATIL] [S.S. SHINDE] JUDGE JUDGE npj/wp3574-2016