IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO.9588 OF 2022 IN FIRST APPEAL ST. NO. 9469 OF 2021 Ashok Cooperative Sugar Factory Applicant

Versus

The New India Assurance Co. Ltd.

and another Respondents Mr. R. B. Temak, advocate for the Applicant CORAM : SANDIPKUMAR C. MORE J.

DATE : 15th September, 2022.

PC :

Heard.

The delay is of only 195 days, which appears to be caused due to Covid-19 pandemic situation. None appears for the non applicants, despite service. As such, the delay of 195 days stands condoned.

The appeal be placed for admission after removal of office obcections, if any.

Civil Application is disposed of.

(SANDIPKUMAR C. MORE) JUDGE adb