Executive Engineer Urdhava Pravara Project Dam Division, Ghulewadi Irrigation Colony, Sangamner v. The State Of Maharashtra And ORS
906ca5763.18
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD 906 CIVIL APPLICATION NO.5763 OF 2018 IN FAST/9057/2018 EXECUTIVE ENGINEER URDHAVA PRAVARA PROJECT DAM DIVISION, GHULEWADI IRRIGATION COLONY, SANGAMNER
VERSUS
THE STATE OF MAHARASHTRA AND ORS ...
Advocate for Applicant : Mr.Solshe Vinesh C.
AGP for Respondent No. 1-State : Mr.A.B.Chate Advocate for Respondent Nos. 1A to 1C : Mr. Mr.Vinod Bhide ...
CORAM : SANDIPKUMAR C. MORE, J.
DATE : 27/01/2023.
PER COURT :
1.
The legal representatives of respondent No. 2 are already brought on record. Whereas respondent No. 3 was dead since beginning and her legal heirs in the form of deceased respondent No. 2 was already on record. 2.
The learned counsel Mr.Vinod Bhide causes appearance on behalf of respondent No. 2A to 2C. 3.
Heard rival submissions. The acquiring body is seeking condonation of delay of 338 days, which appears to
906ca5763.18 be caused due to obtaining sanctions of various stages. There is no strong objection from other side, hence, delay of 338 days stands condoned. Appeal be placed for admission after removal of office objections if any. Application is disposed of.
( SANDIPKUMAR C. MORE ) JUDGE mahajansb/