IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD CIVIL APPLICATION NO. 5757 OF 2018 IN FAST/9265/2018 WITH CIVIL APPLICATION NO. 5759 OF 2018 IN FAST/9276/2018 EXECUTIVE ENGINEER URDHAVA PRAVARA PROJECT DAM DIV. GHULEWADI IRRIGATION COLONY, SANGAMNER, AHMEDNAGAR

VERSUS

THE STATE OF MAHARASHTRA AND ANOTHER ...

Mr. Vinesh C. Solshe, Advocate for Applicant Mr. D.B. Bhange, AGP for Respondent No.1 Mr. V. Y. Bhide, Advocate for Respondent Nos. 2A to 2E ...

CORAM : NITIN B. SURYAWANSHI, J.

DATE : 20th DECEMBER, 2023 PER COURT :

1.

Heard.

2.

For the reasons stated in paragraph No.3 of both the civil applications, civil applications are allowed in terms of prayer clause 'B'. Delay of 248 days is condoned. Appeals be registered. (NITIN B. SURYAWANSHI, J.) SVH