Executive Engineer Urdhava Pravara Project Dam Div. Ghulewadi Irrigation Colony, Sangamner v. The State Of Maharashtra And ANR
2023:BHC-AUG:26874 1 914-CA-5757-18.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD CIVIL APPLICATION NO. 5757 OF 2018 IN FAST/9265/2018 WITH CIVIL APPLICATION NO. 5759 OF 2018 IN FAST/9276/2018 EXECUTIVE ENGINEER URDHAVA PRAVARA PROJECT DAM DIV. GHULEWADI IRRIGATION COLONY, SANGAMNER, AHMEDNAGAR
VERSUS
THE STATE OF MAHARASHTRA AND ANOTHER ...
Mr. Vinesh C. Solshe, Advocate for Applicant Mr. D.B. Bhange, AGP for Respondent No.1 Mr. V. Y. Bhide, Advocate for Respondent Nos. 2A to 2E ...
CORAM : NITIN B. SURYAWANSHI, J.
DATE : 20th DECEMBER, 2023 PER COURT :
1.
Heard.
2.
For the reasons stated in paragraph No.3 of both the civil applications, civil applications are allowed in terms of prayer clause 'B'. Delay of 248 days is condoned. Appeals be registered. (NITIN B. SURYAWANSHI, J.) SVH