The Ex. Engineer, Irrigation Project Div. Latur Thr Gmidc, Aurangabad v. Chandrahas Pandharinath Patil And ORS
1 950 ca 6877-21+
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 950 CIVIL APPLICATION NO.6877 OF 2021 IN FAST/9758/2021 WITH CIVIL APPLICATION NO.6878 OF 2021 IN FAST/9758/2021 THE EX. ENGINEER, IRRIGATION PROJECT DIV. LATUR THR GMIDC, AURANGABAD
VERSUS
CHANDRAHAS PANDHARINATH PATIL AND ORS ...
Advocate for Applicant : Mr. M. C. Swami AGP for Respondent Nos. 2 & 3: Mr. S. N. Kendre Advocate for Respondent No.1 : Mr. H. B. Nandagavale ....
CORAM :
SANDIPKUMAR C. MORE, J.
DATED : 11/10/2022.
P. C. :
IN CIVIL APPLICATION NO.6877 OF 2021 1.
Heard rival submissions.
2.
The applicant acquiring body is seeking condonation of delay of 1251 days. The learned counsel for the original claimants strongly opposed the same. However, for the reasons stated in the application, the aforesaid delay of 1251 days stands condoned. 3.
The appeal be placed for admission after removal of offce objections, if any. The application is accordingly disposed of. IN CIVIL APPLICATION NO.6878 OF 2021:
1.
In view of the statement made by the learned counsel for the applicant acquiring body, there shall be interim stay to the
2 950 ca 6877-21+ execution of impugned award subject to deposit of entire amount of compensation within 14 weeks.
( SANDIPKUMAR C. MORE, J. ) VS Maind/-