The Ex. Engineer, N.D.P.D. Selu, Thr Jalna Irrigation Div, Jalna And ORS v. Abdul Farhan Abdul Razak
ca8546.17
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
AURANGABAD BENCH, AURANGABAD CIVIL APPLICATION NO. 8546 OF 2017 IN FIRST APPEAL ST. NO. 10028 OF 2017 The Executive Engineer N.D.P.D. Selu, through Jalna Irrigation div. Jalna and ors.
... Applicants
VERSUS
Abdul Farhan Abdul Razak ... Respondent .....
Mr. R.C.Patil, advocate for the applicant no.1 Mr. A.M.Phule, A.G.P for applicant nos. 2 and 3 Mr. A.H.Koralkar, adv. for respondent .....
CORAM : K.L.WADANE, J.
DATED : 23rd AUGUST, 2017 O R D E R :
This is an application for stay to the execution of award passed by the Reference Court. Learned counsel appearing for the applicant submits that the appellant is ready to deposit amount of compensation in this Court within a period of 12 weeks.
In view of above, the execution and operation of the award under challenge is stayed
ca8546.17 subject to deposit of amount of compensation together with interest in this Court within a period of 12 weeks.
Civil Application is disposed of.
(K.L.WADANE, J.) dbm