Bombay High CourtCA/7684/2015withdrawn

The Executive Engineer,Jalna And Others v. Prakash Gangadhar Shevlikar

2023-12-09Lok Adalat2 pages

2023:BHC-AUG:26254

IN THE NATIONAL LOK ADALAT PRESIDED OVER BY

HON'BLE SHRI JUSTICE R. M. JOSHI, HELD ON 9th DECEMBER, 2023 AT HIGH COURT LEGAL SERVICES SUB-COMMITTEE AT AURANGABAD FIRST APPEAL NO.3171 OF 2019 WITH CA/7199/2020 IN FA/3171/2019 WITH CA/7684/2015 IN FA/3171/2019 THE EXECUTIVE ENGINEER, JALNA AND OTHERS

VERSUS

PRAKASH GANGADHAR SHEVLIKAR ...

Mr. U. K. Patil, Advocate for the appellants Mr. S. K. Shirse, AGP for the State Mr. Prakash Digambarrao Phulwalkar, Sub Divisional Officer, M.I. Sub Division Ambad

ORDER

(9th December, 2023) 1.

Parties are present along with their respective Advocates. 2.

Learned counsel for the appellants has placed on record the authority given to the Executive Engineer for withdrawal of the appeal. He seeks withdrawal of the appeal on behalf of Executive Engineer. Mr. P. D. Phulwalkar, Sub Divisional Officer is duly identified by Mr. U.K. Patil, learned counsel and Mr. S. K. Shirse, learned AGP. 3.

Admittedly this appeal is in respect of the compensation granted which is within four times and duly covered by the Government Resolution dated 03/11/2016 with corrigendums dated 23/02/2017 and 107.fa3171.19.odt

13/08/2018. Hence, appeal stands disposed of as withdrawn. 4.

Respondent is permitted to withdraw remaining amount deposited in this Court along with accrued interest thereon. 5.

No order as to costs.

6.

Refund of Court fees be proceeded as per rules. 7.